In a small team it is common to spend more time building the schedule than doing the work. This guide introduces a step-by-step way to run a Gantt chart that is light to create and light to change.
When a small team actually needs a Gantt chart
Work done by three or four people can run on conversation alone, but things change once tasks start waiting on each other. When design must finish before development and development before testing, a single picture helps a great deal.
A Gantt chart shows who does what and when, and how far everything slips if one task runs late. If all the tasks are independent, however, a plain to-do list is better. Choose the tool to match the need.
A Gantt chart earns its place when tasks wait on each other or deadlines are fixed
For solo work or unrelated chores, a to-do list is enough
It is also a good one-page answer when you must explain the schedule to a client or manager
Splitting work into sensible sizes
A single task should be roughly one day to one week long. If it is too large you cannot see progress, and if it is too small you spend your time just editing the chart. Instead of design, try draft sketch, review and revision, and final approval.
Name each task with a verb and a result so that it is easy to judge whether it is done. A task called website work gives no sign of when it ends, but approve the first-screen draft has a clear end.
Phrase task names as an action plus an outcome, for example approve the first-screen draft
Give each task exactly one owner and put helpers in a note
Keep the whole chart to about fifteen rows on one page
Estimating durations and dependencies
Base durations on what usually happens rather than the ideal case, and if you have done similar work, use how long it really took. Also check that no one has overlapping bars, since one person cannot do two tasks at the same time.
Mark a dependency only when one task truly has to finish before another can start. The longest chain of linked tasks decides the overall schedule and is called the critical path, so protect the tasks on it first and report immediately if one slips.
Set the start date and enter only durations so that end dates follow automatically
If one person's bars overlap, postpone one or hand it to someone else
Highlight the longest chain with a noticeable color
Buffers and milestones
Unexpected work always creeps in. Rather than padding every task, it is easier to manage buffers grouped in the middle and before the end. For example, leave about a tenth of the total time empty before the deadline.
A milestone is a one-day marker with no duration, placed where the team checks something together, such as draft approval or a midpoint report. With milestones, a long schedule breaks into several small deadlines and keeps attention up.
Place buffer as one block before the deadline, not on each task
Set one milestone every two or three weeks and name it after a result
If the deadline is imposed from outside, count backward to find when to start
A weekly check-in habit, and the tool on this site
A Gantt chart is not a document you make once but a tool you refresh weekly. Meet for about ten minutes once a week, mark finished work, and move late tasks to new dates together with the reason. Reasons you wrote down become evidence for the next estimate.
The Gantt chart on this site draws the picture from tasks and dates written as text, so anyone on the team can edit it. If you save the previous picture as an image before big changes, you can show how far the schedule has moved.
Spend ten minutes on the same day and time each week to review done, late and new items
Do not delete late tasks; keep them with the reason and the new date
When a major change happens, save the earlier picture and use it as explanatory material